We are Open for Business!

We are very excited to announce that the new study spaces on the Lower Ground Floor are now open!

We know how hard it can be to find a study spot, so we listened to our students and added 358 new study spaces to the Main Library over the summer, as this blog has documented. Today we celebrated the grand opening of the Lower Ground Floor, which has been renovated for student use.

 blog-1

Bryan MacGregor, Director of User Services and Alec Edgecliffe-Johnson, President of the Edinburgh University Students’ Association, did the honours, cutting the ribbon to officially open the new spaces.

blog-2

In the coming weeks we will be running competitions in the new space, so keep your eye on our Facebook and Twitter for the chance to win prizes! We would also love to hear your feedback about the new spaces, and about any further changes you want to see in the Library, so please get in touch via Facebook or Twitter, or use the survey forms we will be distributing in the Lower Ground Floor.

We hope that these new study spaces will make the upcoming deadlines a little easier!

 

Nearly there!

Everything is almost ready for the study spaces on the Lower Ground Floor of the Main Library to open, we just have a few last minute things to put in place for you and the space will be open to students on Monday 17th October.

 All of the new furniture has been delivered and the new desktop power outlets have been put in place to make your studying here as easy as possible.

blog-1

We’ve got new signs on the lower ground floor directing you to the space too!

blog-2

Come and see the space on Monday and let us know what you think!

 

New Furniture Arriving

We are almost there – thanks for your continued patience!

 New furniture for the 358 additional study spaces will start to arrive next week – please see below for details.

 Tuesday 13th September – 2nd & 4th Floors

Thursday 15th September – Lower Ground Floor

Tuesday 20th September – 1st & 3rd Floors

 Whilst every attempt will be taken to avoid the minimum of disruption to users as the new furniture is assembled there will be an element of unavoidable noise as these works get carried out.

 The installation of the new desk top power modules will be installed quickly after the new study desks have been assembled, the desktop power will enable you to charge your devices via a plug or a USB port. These works will be carried out in the evening as there will be an element of drilling work involved.  As with previous works, barriers will be put in place to alert users of the areas where the contractors will be working in.  

 Tuesday 13th , Wednesday 14th & Thursday 15th September – 2nd & 4th Floors

Monday 19th September – Lower Ground Floor

Tuesday 20th &  Wednesday 21st September –   1st & 3rd Floor

 

 

 

Evening Floor Closures

As part of the ongoing electrical enabling works to accommodate the new study desks as part of the library refurbishment works, our contractors have scheduled a series of essential power shut downs from Monday 5th September 2016. The shut downs will be taking place from 21:00 to minimise disruption to library users.  On these dates, the following floors will be closed to both staff and library users whilst the works are being carried out:

Mon 5th September: 4th and 3rd floors closed from 21:00 (to 06:00 Tues 6th)

Tues 6th September: 2nd floor closed from 21:00 (to 06:00 Weds 7th)

Weds 7th September: 1st floor and Lower Ground Floor closed from 21:00 (to 06:00 Thurs 8th)

There will be no access to the closed floors from 21:00 until the library opens the following morning. Please be advised to collect items in advance of or after the dates and times above. Staff have been advised of any preparation required in advance of the power shut downs.

Apologies for the disruption caused – thank you for your patience while work is underway.

Desk Top Power Modules

Part of the refurbishment works to create new study areas will also involve an upgrade to the existing desk top power modules on a number of new and existing desks.  We are confident that these new desk top power modules will help address the many issues that users have been experiencing, each desk will be fitted with a single socket and double USB charging point.

 Additional electrical enabling works have been planned to accommodate these new desk top power modules which will see a number of areas affected, these works have been scheduled in order to minimise disruption to users.  These areas will be cordoned off to users whilst the work is taking place.

 Please see below for details

 4th Floor: from 6pm to 6am on Monday 29th August – Tuesday 30th August 2016 electrical enabling work will take place throughout the floor to prepare for the installation of additional desk top power supply units.

 3rd Floor: from 6pm to 6am on Tuesday 29th August – Wednesday 31st August 2016 electrical enabling work will take place throughout the floor to prepare for the installation of additional desk top power supply units.

 2nd Floor: from 6pm to 6am on Wednesday 31st August, Thursday 1st & Friday 2nd September 2016 electrical enabling work will take place throughout the floor to prepare for the installation of additional desk top power supply units.

 1st Floor: from 6pm to 6am on Thursday 1st September – Friday 2nd September 2016 electrical enabling work will take place throughout the floor to prepare for the installation of additional desk top power supply units.

 

 

Main Library Summer Improvements 2016 – Update 18th August

Work is continuing in the Main Library on a programme of works to bring significant improvements for library users through increasing the number of study spaces by 350 and providing additional power and data facilities at study desks.

Work underway this week (22nd – 31st August)

1st  floor – construction and electrical enabling work will now begin in what was the ‘New Book Area’ and ‘Reception Desk’ to transform these area into new study spaces. In addition to these works, study desks adjacent to accessible study rooms 8 – 11 will also undergo upgrade which will include desk top power being installed to these desks. Please be aware that whilst these works are being carried out,  temporary diversions will be put in place to both the meeting room suite and south side study area.  Directional signage providing alternative access to these areas will be placed on 1st floor to assist you.

Lower Ground Floor – construction work has also now started in this area and will continue throughout the rest of August.

Apologies for the continuing noise and disruption – thank you for your patience while work is underway.

Students PC’s Deep Clean

Please note PC’s and Key Boards within the Ground, 1st and 2nd Floors will undergo a deep clean from Monday 15th August. The contractors  will start from the 2nd floor and then continue to the ground floor, the work is likely to last approximately 3 days.  PC’s will be temporarily unavailable whilst the deep clean  is undertaken which includes keyboard and monitor sanitising. PC’s will then quickly become available on each floor as the cleaning contractors progress to all areas of the floor.

Thank you for your patience.

Blog post

 

Main Library Summer Improvements 2016 – Update 9th August

 Work is continuing in the Main Library on a programme of works to bring significant improvements for library users through increasing the number of study spaces by 350 and providing additional power and data facilities at study desks.

Work underway this week (8th-15th August)

3rd floor – Construction work to remove empty shelves and carry out electrical works is underway on the south side of the 3rd floor. The collections PC-Q are currently cordoned off and access to these items is through consultation with Helpdesk staff located on the 3rd floor or Ground Floor 9.15-4.45 Monday to Friday, or through emailing collections-management@ed.ac.uk at other times.

 Apologies for the continuing noise and disruption – thank you for your patience while work is underway.

Blog 2           blog 1

Electrical work underway on the 3rd floor              Shelving being removed  on the                                                                                                        3rd floor

 

 

 

Main Library Summer Improvements 2016 – Update 3/8/2016

 

Work is continuing in the Main Library on a programme of works to bring significant improvements for library users through increasing the number of study spaces by 350 and providing additional power and data facilities at study desks.

Work underway this week (1st-8th August) and updates

2nd floor – Construction work to remove empty shelves and carry out electrical works is underway on the north side of the 2nd floor. The collections JV-PB are currently cordoned off and access to these items is through consultation with Helpdesk staff located on the 2nd floor or Ground Floor 9.15-4.45 Monday to Friday, or through emailing collections-management@ed.ac.uk at other times.

Move of collections 3rd floor to 2nd floor

Collections from the 3rd floor now permanently located on the 2nd floor are:

  • All P Pamphlets
  • All P Folios
  • P books
  • PA books
  • PB books

Signs

The updating of shelf-end signs is currently underway and we expect this to be completed this week.

We are also working on updating the main Library signs and will have accurate signs in place at the completion of the Main Library works.

DiscoverEd Search Points

We are currently updating the information in DiscoverEd and the information retrieved will then reflect the new location of items that have moved from the 3rd floor to the 2nd floor.

Compression of Compressions

The addition of new study spaces on the 2nd, 3rd and 4th floors is made possible through the compression of the collections on the shelves to provide free shelving that can be removed. This compression of collections is now complete.

Apologies for the continuing noise and disruption – thank you for your patience while work is underway.