Desk Top Power Modules

Part of the refurbishment works to create new study areas will also involve an upgrade to the existing desk top power modules on a number of new and existing desks.  We are confident that these new desk top power modules will help address the many issues that users have been experiencing, each desk will be fitted with a single socket and double USB charging point.

 Additional electrical enabling works have been planned to accommodate these new desk top power modules which will see a number of areas affected, these works have been scheduled in order to minimise disruption to users.  These areas will be cordoned off to users whilst the work is taking place.

 Please see below for details

 4th Floor: from 6pm to 6am on Monday 29th August – Tuesday 30th August 2016 electrical enabling work will take place throughout the floor to prepare for the installation of additional desk top power supply units.

 3rd Floor: from 6pm to 6am on Tuesday 29th August – Wednesday 31st August 2016 electrical enabling work will take place throughout the floor to prepare for the installation of additional desk top power supply units.

 2nd Floor: from 6pm to 6am on Wednesday 31st August, Thursday 1st & Friday 2nd September 2016 electrical enabling work will take place throughout the floor to prepare for the installation of additional desk top power supply units.

 1st Floor: from 6pm to 6am on Thursday 1st September – Friday 2nd September 2016 electrical enabling work will take place throughout the floor to prepare for the installation of additional desk top power supply units.

 

 

Main Library Summer Improvements 2016 – Update 18th August

Work is continuing in the Main Library on a programme of works to bring significant improvements for library users through increasing the number of study spaces by 350 and providing additional power and data facilities at study desks.

Work underway this week (22nd – 31st August)

1st  floor – construction and electrical enabling work will now begin in what was the ‘New Book Area’ and ‘Reception Desk’ to transform these area into new study spaces. In addition to these works, study desks adjacent to accessible study rooms 8 – 11 will also undergo upgrade which will include desk top power being installed to these desks. Please be aware that whilst these works are being carried out,  temporary diversions will be put in place to both the meeting room suite and south side study area.  Directional signage providing alternative access to these areas will be placed on 1st floor to assist you.

Lower Ground Floor – construction work has also now started in this area and will continue throughout the rest of August.

Apologies for the continuing noise and disruption – thank you for your patience while work is underway.

Students PC’s Deep Clean

Please note PC’s and Key Boards within the Ground, 1st and 2nd Floors will undergo a deep clean from Monday 15th August. The contractors  will start from the 2nd floor and then continue to the ground floor, the work is likely to last approximately 3 days.  PC’s will be temporarily unavailable whilst the deep clean  is undertaken which includes keyboard and monitor sanitising. PC’s will then quickly become available on each floor as the cleaning contractors progress to all areas of the floor.

Thank you for your patience.

Blog post

 

Main Library Summer Improvements 2016 – Update 9th August

 Work is continuing in the Main Library on a programme of works to bring significant improvements for library users through increasing the number of study spaces by 350 and providing additional power and data facilities at study desks.

Work underway this week (8th-15th August)

3rd floor – Construction work to remove empty shelves and carry out electrical works is underway on the south side of the 3rd floor. The collections PC-Q are currently cordoned off and access to these items is through consultation with Helpdesk staff located on the 3rd floor or Ground Floor 9.15-4.45 Monday to Friday, or through emailing collections-management@ed.ac.uk at other times.

 Apologies for the continuing noise and disruption – thank you for your patience while work is underway.

Blog 2           blog 1

Electrical work underway on the 3rd floor              Shelving being removed  on the                                                                                                        3rd floor

 

 

 

Main Library Summer Improvements 2016 – Update 3/8/2016

 

Work is continuing in the Main Library on a programme of works to bring significant improvements for library users through increasing the number of study spaces by 350 and providing additional power and data facilities at study desks.

Work underway this week (1st-8th August) and updates

2nd floor – Construction work to remove empty shelves and carry out electrical works is underway on the north side of the 2nd floor. The collections JV-PB are currently cordoned off and access to these items is through consultation with Helpdesk staff located on the 2nd floor or Ground Floor 9.15-4.45 Monday to Friday, or through emailing collections-management@ed.ac.uk at other times.

Move of collections 3rd floor to 2nd floor

Collections from the 3rd floor now permanently located on the 2nd floor are:

  • All P Pamphlets
  • All P Folios
  • P books
  • PA books
  • PB books

Signs

The updating of shelf-end signs is currently underway and we expect this to be completed this week.

We are also working on updating the main Library signs and will have accurate signs in place at the completion of the Main Library works.

DiscoverEd Search Points

We are currently updating the information in DiscoverEd and the information retrieved will then reflect the new location of items that have moved from the 3rd floor to the 2nd floor.

Compression of Compressions

The addition of new study spaces on the 2nd, 3rd and 4th floors is made possible through the compression of the collections on the shelves to provide free shelving that can be removed. This compression of collections is now complete.

Apologies for the continuing noise and disruption – thank you for your patience while work is underway.